Services Provided
Construction Documents
Bid Phase Services
Construction Phase Services

Completion
2008-2013

Location
Tulsa, Oklahoma

Client
River Parks Authority
& City of Tulsa

 

 

 

 

 

Funded by the George Kaiser Family Foundation and the City of Tulsa the $15 million River Parks Trail Enhancement project consists of 12 miles of improvements to both the east and west bank from 11th Street to 71st Street. The planned dual trail provides a trail for the cyclist and a separate trail for the pedestrians and runners on both sides of the river. These dual trails are separated by landscaped greenspace. Where separation is not feasible the trail is widened from 10’ to 18-20’ to accommodate pedestrians and cyclists. New signage will direct pedestrians and cyclists, while new trail lighting will provide safety for evening and early morning recreation.